01 · The situation
A plan too slow to steer by
The corporate financial plan was a static, consultant-built model. Each re-run took two days, so by the time a scenario came back the question had usually moved on. Assumptions changed without a clear owner, and leadership discussions centred on the last version rather than the next decision.
02 · What I did
Rebuilt the plan as a governed system, not a bigger spreadsheet
- Rebuilt the corporate model top-down, modular and auditable, cutting run-time complexity.
- Added an assumptions register: every critical input tiered, owned and logged, with material changes escalated.
- Linked it to a risk register and a scenario engine, so timing, pricing, cost and funding could be stress-tested on demand.
- Put a monthly business review on top, so the model drives the monthly executive conversation instead of reporting the past.
03 · The decision it enabled
Bringing Phase 2 forward, tested in the room
With re-runs in two minutes, the Management Committee could see the effect of a change before it decided, not two days after.
Development phasing
The Committee was able to assess the financial implications of bringing forward Phase 2 versus retaining the original development programme, including the impact on peak equity requirements, cash flow and overall project returns.
04 · The outcome
What other Boards can take from this
Speed without governance just produces wrong answers faster. The gain came from pairing a faster model with owned assumptions and a monthly rhythm, so the leadership team could trust the number it was looking at.